Project guide · No 1 of 8

Variations & instructions

A change arrives on site before its price or paperwork is settled. YPA keeps the instruction, cost, approval and payment evidence together, so you can see what needs confirming and what to do next.

How this helps a contractor

For a contractor, this keeps the instruction, supporting record, price request and response status connected before changed work disappears into the job. An appointed quantity surveyor, principal agent or project manager may review the relevant evidence as an invited collaborator, but YPA does not assess, approve or instruct the change for them.

Start with the contractor’s project question and the records already available. Each participant’s private questions and drafts remain separate from shared project records. At setup, we agree the invited collaborators, information and recipients that help the contractor move the work. How personal support and collaboration work. See the contractor questions YPA helps answer.

What YPA does

Start with what you have. Share the accepted scope or contract, the relevant plans, instructions, quotations and approvals. Certificates and payment evidence let YPA follow the change through to cash. Existing registers help if you have them; YPA can create its own from your records.

YPA creates and maintains the sheet from your records. Its entries are marked system-generated, yours to verify. Review and edit at any time. Drafts come to you; you check and send them yourself.

How it actually runs

Where it usually goes wrong

  • A verbal change has no clear record of who instructed it or when.
  • A price is quoted but never agreed, or an agreed change is missing from certification.
  • A certificate is treated as proof of payment before the receipt is checked.
  • An unpriced item is hidden inside a total as though its cost were zero.

What a YPA sheet looks like

One row per change keeps the description, instruction, price and review status together. The example uses the same Project A records as the explainer. All columns remain available by scrolling the sheet horizontally.

YPA
Variations & instructionsProject A · contractor-side example · as at 6 September 2026
Variation NumberDateDescriptionInstruction ReferenceOriginatorCost CodeReasonWork StatusQuoted AmountQS ValuationApproved AmountTime Impact (days)StatusVerified BySource Tag
VO-042026-07-10Additional foundation depthSI-004AgentFNDGround conditionCompleteR 38 400,00R 38 400,00R 38 400,002PaidContractorsystem-generated
VO-052026-08-14Revised window sill heightSI-005AgentWINDesign revisionNot startedR 26 500,00R 26 500,00R 26 500,00To confirmAgreedContractorsystem-generated
VO-062026-08-20Roof flashings — Block CSI-006AgentRFGRevised detailNot startedR 18 500,00Not receivedNot approvedTo confirmPricedNot yet verifiedsystem-generated
VO-072026-09-03Cladding finish — elevation AVariation Instruction 07AgentCLDAgent instructionNot startedTo be pricedNot receivedNot approvedTo confirmInstructedNot yet verifiedsystem-generated
VO-082026-09-04Additional stone return — elevation ASI-008 · review requiredContractor — for reviewCLDSite photo and voice noteNot startedTo be pricedNot receivedNot approvedTo confirmFor reviewNot yet verifiedsystem-generated
VO-092026-09-04Door ironmongery adjustmentSI-009AgentDRSDesign coordinationNot startedTo be pricedNot receivedNot approvedTo confirmInstructedNot yet verifiedsystem-generated
R18,500 quoted but not yet agreed · 3 changes still to be pricedsystem-generated · yours to verify
Illustrative example · system-generated entries are yours to verify · review and edit your sheet at any time.

What you can do today

Want the full picture?

Your personal project assistant in WhatsApp and email. Start with one question, on your own or with collaborators whose access is agreed individually. Each participant has a private conversation with YPA. YPA is available through application, with the project scope, service and price agreed before you start.

This guide is general information, not legal advice. What counts as a valid instruction, and how variations are priced and approved, comes from your signed contract — always check the contract before acting. YPA helps you record, track and draft; it doesn't give legal opinions.