Variations & instructions

A change to the work arrives on WhatsApp on a Friday afternoon — and before anyone has priced it, the work has often already happened. Unpriced and unapproved changes are where the money on a job leaks: not because the work was bad, but because the change was never dated, priced and approved while it still could be.

What YPA does

Every draft YPA writes comes to you for review first — short messages on WhatsApp, documents by email. Nothing goes out until you send it yourself.

How it actually runs

Where it usually goes wrong

The four ways a variation costs you:

  • The verbal instruction — "just get on with it" on a call or a site visit. No date, no paper, no reference.
  • The unpriced change — work starts before the cost is agreed. By the time it's priced, there's no leverage left.
  • The unapproved extra — signed off on site but never reflected in a certificate or a payment.
  • The disputed change — when the client says "we never asked for that", the only answer is a dated record with the instruction reference. Without it, the cost sits with the contractor.

What a YPA sheet looks like

Every instruction and change goes onto the YPA Variation Register — one row per change, dated, with the money and the status at each step. The Cost Code column groups changes by trade (FND foundations, WIN windows, CLD cladding) — the same categories your QS works in.

YPA
YPA — Your Project Assistant · Variation Register Example project · generated sheet format
VO NoDateDescriptionInstruction RefOriginatorCost CodeReasonWork StatusQuoted AmountQS ValuationApproved AmountTime Impact (days)StatusVerified BySource Tag
VO-012026-01-09Extra foundation depth – Block ASI-004Principal agentFNDChange of soil conditionComplete38,40038,40038,4003PaidQSEmail
VO-022026-01-22Move boundary wall 2 mSI-005ClientEXTClient requestComplete72,50072,50072,5005PaidQSWhatsApp
VO-032026-02-12Windows – revised sill heightSI-008ArchitectWINDesign revisionComplete28,60026,50026,5002PaidQSEmail
VO-042026-03-05Additional steel lintels – garageSI-014ClientSTLClient requestComplete38,40037,20037,2002PaidQSWhatsApp
VO-052026-03-24Stormwater – extra outletSI-016EngineerCIVEngineer's instructionComplete41,90041,90041,9004PaidQSEmail
VO-062026-04-14Stone cladding – balcony changeSI-019ArchitectCLDDesign revisionComplete56,00053,20053,2006PaidQSVoice note
VO-072026-05-06Tiling – larger format, labour onlySI-021ClientTILClient requestNot started41,9003PricedQSWhatsApp
VO-082026-05-21Roof sheeting – colour changeSI-022ClientRUFClient requestNot started18,9001PricedQSEmail
VO-092026-05-27Move boundary wall 2 m (extra)Verbal (site)EXTDisputed scopeNot startedDisputedQSSite meeting
VO-102026-06-03Security gate – keypad upgradeSI-024ClientSECClient requestNot started2InstructedQSWhatsApp
Exposure: R60,800 priced but not yet approvedYPA flags the unpriced and unapproved rows →
Example only — illustrative rows in the real YPA Variation Register sheet format.

What you can do today

Want the full picture?

We've built YPA for the way African construction projects actually work. YPA is the site file with a memory. YPA is onboarding its first live builds in small, limited cohorts. Pilot places are free for a defined period — and if we ever charge, the plan and its price will be shown to you before anything is billed.

This guide is general information, not legal advice. What counts as a valid instruction, and how variations are priced and approved, comes from your signed contract — always check the contract before acting. YPA helps you record, track and draft; it doesn't give legal opinions.