What you owe

Your payment tracker watches the money coming in. The payables register watches the money going out — the subcontractor invoices, the supplier statements, the retention you hold on their work. Most contractors know what they're owed to the rand but only roughly what they owe — and the gap is where cash flow gets squeezed: the certificate lands late, but the wages don't wait.

What YPA does

YPA never pays anyone. It watches the dates and keeps the record, so you pay on your terms — never late by accident, never early by forgetfulness.

How it actually runs

Where it usually goes wrong

Why "roughly" is the expensive word:

  • The due date nobody saw — a subbie's invoice falls due the same week the client's certificate is late. The subbie doesn't care whose certificate is late; the wages are Friday.
  • The invoice that arrived and vanished — handed over on site or photographed on a phone, then lost in the shuffle until the supplier phones about it.
  • The supplier statement that "doesn't match" — and there's no single record of what was invoiced, paid and still open to check it against.
  • Retention held, forgotten — months after the subcontractor's work was released, their retention still sits unpaid because the release date passed unmarked.

What a YPA sheet looks like

Every invoice goes onto the YPA Payables Register — one row per invoice, with the due date, the paid date and the balance.

YPA
YPA — Your Project Assistant · Payables Register Example project · generated sheet format
Invoice NoSupplierDescriptionAmountDue DatePaid DatePaid AmountOutstandingStatusVerified BySource Tag
INV-2204STEEL-SASteel fixings – Block A124,5002026-08-052026-08-04124,500PaidEmail
INV-2208CON-SUPReady-mix – Block B slab312,0002026-08-192026-08-18312,000PaidWhatsApp
INV-2211PLUM-SUPSanitary ware – Block A78,0002026-08-262026-08-2578,000PaidEmail
INV-2214STEEL-SAStructural steel – Block B frame412,0002026-09-08412,000DueEmail
INV-2216TILE-HOUSEPorcelain tiles – communal96,0002026-09-1296,000DueEmail
INV-2217ELEC-PROSwitchgear – main DB deposit25,8002026-09-1525,800DueEmail
INV-2219JOIN-WORKSTimber doors – Block A142,0002026-09-19142,000DueEmail
INV-2220ALU-SUPWindows – Block A deposit85,8002026-09-2285,800DueWhatsApp
INV-2221Subbie – TilingTiling labour – communal (retention held)156,0002026-10-02156,000DueEmail
INV-2222Subbie – Steel erectorsErection – Block B frame98,0002026-10-0598,000DueEmail
Open: R1,015,600 · next due 2026-09-08YPA tells you each morning what falls due →
Example only — illustrative rows in the real YPA Payables Register sheet format.

What you can do today

Want the full picture?

We've built YPA for the way African construction projects actually work. YPA is the site file with a memory. YPA is onboarding its first live builds in small, limited cohorts. Pilot places are free for a defined period — and if we ever charge, the plan and its price will be shown to you before anything is billed.

This guide is general information, not legal advice. Payment terms, retention and release triggers for your subcontractors come from your signed subcontracts and the main contract — always check the contract before acting. YPA helps you track; it doesn't give legal or tax opinions.