Notices & deadlines

Many disputes aren't lost on the merits — they're lost on notice: the clause that required written notice within a set number of days, the problem raised on a call instead, the window gone by the time it mattered. A missed window is a lost right, and the windows often pass unwatched.

What YPA does

Every notice and follow-up YPA drafts comes to you for review first. Nothing goes out until you send it yourself.

How it actually runs

Where it usually goes wrong

The expensive failure is never the deliberate one:

  • The incoming notice that sat in the inbox — arrived on a Friday, its window ran out while nobody was looking.
  • The outgoing notice that should have been sent earlier — sent three weeks after the delay was known, not on the day it first became apparent.
  • The call that should have been a notice — the problem was raised, but not in writing, so the window opened and closed with no record.
  • The deadline nobody wrote down — the extension request, the adjudication response, the reply that had to land within days, and the date lived only in someone's head.

What a YPA sheet looks like

Every notice goes onto the YPA Notices Register — one row per notice, both directions, with the deadline and the action.

YPA
YPA — Your Project Assistant · Notice Register Example project · generated sheet format
Notice NoDirectionTypeSubjectDate IssuedTo / FromEvidence RefDeadlineRequired ActionStatusLinked VO/RFIVerified BySource Tag
N-012026-04-16InInstructionStone cladding – balcony changeArchitect → Youemail 16 Apr2026-04-21Confirm receiptRespondedVO-06Email
N-022026-06-12InDefault noticeAluminium window installation – alleged delayClient → Youemail 12 Jun2026-06-26Reply within windowRespondedEmail
N-032026-06-25OutDelay notificationStormwater drawings lateYou → Clientemail 25 JunFor the recordSentEmail
N-042026-07-08OutExtension of time requestFoundation delay – changed groundYou → Principal agentletter 08 Jul2026-07-22EOT adjudicationClosedVO-01Letter
N-052026-07-15InInstruction – clarifyStop work at boundary wallEngineer → Youemail 15 Jul2026-07-17Confirm receipt + positionRespondedVO-09Email
N-062026-07-28OutVariation noticeTiling – larger format, labour onlyYou → Principal agentWhatsApp 28 Jul2026-09-12Price instructionSentVO-07WhatsApp
N-072026-08-14InNotice of defaultRoofing programme – client concernClient → Youletter 14 Aug2026-09-12Reply within windowReceivedLetter
N-082026-08-20OutDelay notificationWindows – revised sill heightYou → Clientemail 20 AugFor the recordSentVO-03Email
N-092026-09-01OutExtension of time requestLate information – balustrade fixing detailYou → Principal agentemail 01 Sep2026-09-15EOT adjudicationSentRFI-114Email
N-102026-09-04OutPractical completion noticeBlock A – PC claimedYou → Clientletter 04 Sep2026-09-18Client inspectionDraftLetter
4 windows open · next closes 2026-09-12YPA watches the response clocks in your morning brief →
Example only — illustrative rows in the real YPA Notice Register sheet format.

What you can do today

Want the full picture?

We've built YPA for the way African construction projects actually work. YPA is the site file with a memory. YPA is onboarding its first live builds in small, limited cohorts. Pilot places are free for a defined period — and if we ever charge, the plan and its price will be shown to you before anything is billed.

This guide is general information, not legal advice. Which events need notice, in what form and within how many days, comes from your signed contract and the applicable law — always check the contract before acting. YPA helps you record, track and draft; it doesn't give legal opinions.