Meetings, decisions & agreements

The client says it at the site meeting: "We'll confirm the window detail next week — don't let it hold you up." The work starts. The confirmation never comes — and when the invoice does, the answer is: "We never agreed to that." Some of the most expensive words on a project are agreed in a meeting and never written down.

What YPA does

Every confirmation YPA drafts comes to you for review first. Nothing goes out until you send it yourself.

How it actually runs

Where it usually goes wrong

The unwritten agreement is the most expensive document on the job:

  • "We'll confirm next week" — and next week never comes — the work was done on the promise; the other side never confirms, and the cost lands on the job.
  • The site meeting with no minutes — decisions made in the room become "we never agreed to that" in the office.
  • The WhatsApp decision nobody filed — the client's message saying "proceed on the current line" scrolls away, and the record scrolls with it.
  • The promise with no owner and no date — "we'll get back to you" means nothing until it has a who and a when.

Where the line is

An agreement is not an instruction to change the work — that's the Variations Register's job, with its own rules about written authority. And a question is not an agreement — that's an RFI. The log sits between them: it records what was decided and promised, so decisions can feed a variation when the agreed change needs pricing, and promises feed the follow-up when they slip.

What a YPA sheet looks like

Every decision and promise goes onto the YPA Decisions & Agreements Log — one row per agreement, with who, what and when. The log is kept for you: YPA reads it out of the minutes, recordings and messages, and surfaces the un-kept promises in your morning brief.

YPA
YPA — Your Project Assistant · Decisions & agreements log kept for you · read from minutes, messages and voice notes
DateWhat was agreed / promisedWho agreed itForm / recordPromised byStatus
2026-08-25Site meeting: window detail confirmed; formal variation to followClientMinutes (recorded)2026-09-01Overdue
2026-08-25Roofing re-sequence approved – sheeting moved to week 41Client + PAMinutes (recorded)Closed
2026-08-28Boundary wall can proceed on current lineClientWhatsApp messageClosed
2026-08-31Stone cladding: sample to be approved before fixingArchitectEmail2026-09-07Overdue
2026-09-02Cable tray route per mark-upElectrical engRFI-108 responseClosed
2026-09-03Tiling: larger format confirmed, labour onlyClientVoice note2026-09-10Open
2026-09-04Security gate: keypad upgrade to be instructedClientCall (site)2026-09-11Open
2026-09-05Waterproofing spec: garage roof to be confirmedArchitectEmail2026-09-12Open
2 promises overdue · 3 still openYPA surfaces the un-kept confirmations in your morning brief →
Illustrative — the log YPA keeps of what was agreed and promised.

What you can do today

Want the full picture?

We've built YPA for the way African construction projects actually work. YPA is the site file with a memory. YPA is onboarding its first live builds in small, limited cohorts. Pilot places are free for a defined period — and if we ever charge, the plan and its price will be shown to you before anything is billed.

This guide is general information, not legal advice. What makes an agreement or instruction binding comes from your signed contract and the applicable law — always check the contract before acting. YPA helps you record, track and draft; it doesn't give legal opinions.